The short version

  • The second of two new I-270 bridges over the Mississippi is finished but not open yet. IDOT held a ribbon cutting Nov. 9 and planned to open the westbound span Nov. 16. On Nov. 13 it postponed the opening because the bridge's expansion joints need more work. It now expects the bridge to open next weekend.
  • When it opens, each direction gets its own bridge, with two lanes and much wider shoulders than the 1966 bridge they replace.
  • A third lane each way comes next construction season, after crews finish the median, guardrails and painting. The full project costs $531.6 million, split between Illinois and Missouri.

What's happening right now

If you've crossed the river on I-270 since early 2025, you've already been driving on a new bridge. The new eastbound span, the southern of the twin bridges, opened to traffic in December 2024. Since early 2025 it has carried traffic both ways, two lanes in each direction, while crews tore down the old 1966 bridge and built the westbound span in its place.

That westbound span is finished. On Nov. 9, the Illinois and Missouri transportation departments, joined by local legislators and industry partners, cut the ribbon on the twin bridges. Westbound traffic was supposed to move onto its new bridge Monday, Nov. 16.

It didn't. On Nov. 13, IDOT posted an update: "The new westbound I-270 Mississippi River Bridge will not open to traffic Nov. 16 as previously announced. Additional work on the bridge's expansion joints is needed before it can open. The bridge is expected to open next weekend."

Expansion joints are the gaps built into a bridge deck so it can expand and contract with heat and cold without cracking. IDOT hasn't said anything more about what needs fixing. A week's delay to get them right is the kind of delay you want.

Until then, nothing changes. Both directions keep sharing the eastbound bridge. Next weekend falls just before Thanksgiving travel, so if you're crossing that weekend, check IDOT's traveler map at GettingAroundIllinois.com or IDOT District 8 on social media before you go. Expect lane shifts while traffic moves over.


What we know

Why it was replaced. Confirmed. The old bridge opened in 1966. It had two lanes each way and shoulders too narrow for a stalled car or an ambulance, and it needed frequent maintenance and emergency repairs. IDOT says traffic at the crossing has more than doubled since it opened. If you've been stuck behind a breakdown on that bridge, you know what narrow shoulders mean.

What you'll get. Confirmed. Two separate bridges, one for each direction. The westbound span sits on the old bridge's alignment, and the eastbound span sits just south of it. Both have wider shoulders, built so I-270 can grow to three lanes each way.

When the third lane comes. Confirmed. IDOT says median work, guardrails and painting of the girders and beams will be finished next construction season, and the corridor will then open to three lanes in each direction. St. Louis Public Radio reports officials expect that by next summer.

What it costs and who pays. Confirmed. The two bridges cost $496.2 million, shared between Illinois and Missouri, with IDOT overseeing construction. A separate $35.4 million Missouri project rebuilt the Riverview Drive interchange just west of the bridge. Together that's $531.6 million. On the Illinois side, it's part of Gov. JB Pritzker's Rebuild Illinois capital program.

How busy it is. Confirmed. State Rep. Amy Elik said the old bridge carried about 51,000 vehicles a day. MoDOT Director Ed Hassinger said the new one will carry "in excess of 50,000 vehicles a day." About one in five vehicles is a truck.


What we don't know yet

The exact opening day and time. Unconfirmed. IDOT has said "next weekend" and hasn't given a specific day. Watch IDOT District 8 for the announcement.

What was wrong with the joints. IDOT hasn't explained it beyond "additional work." We'll update this story if it does.

A firm date for the third lane. Unconfirmed. "Next construction season" and "by next summer" are the official guidance, weather permitting.


Not the same bridge

Two different bridges carry the "Chain of Rocks" name. The Old Chain of Rocks Bridge, the 1929 bridge with the famous bend in the middle, still stands just downriver. It's been closed to cars for decades and is open to walkers and bicyclists. The bridge being replaced is the New Chain of Rocks Bridge that carries I-270. "New" has been its name since 1966, so it's now a new New Chain of Rocks Bridge.


Why it matters here

It's our front door to north St. Louis County. For Granite City, Mitchell, Pontoon Beach and anyone using I-270 from Edwardsville, Glen Carbon, Collinsville, Maryville or Troy, this is the main crossing to Lambert Airport, north county jobs and the west side of the metro. Separate bridges, wider shoulders and eventually a third lane should mean fewer crawls past breakdowns and quicker work for first responders.

It's built for freight, and freight means jobs. Our side of the river has filled with warehouses along I-270 and I-255. The St. Louis Regional Freightway says nearly 70% of the region's industrial tenants in buildings over 500,000 square feet are within 10 minutes of the larger I-70 corridor. "This is a critical freight link for businesses across the Metro East," said State Rep. Katie Stuart, D-Collinsville.

Both parties claimed it, and both states paid for it. State Sen. Erica Harriss, R-Edwardsville, called two states investing half a billion dollars together a strong example of cooperation. Big projects across a state line don't happen often, and this one held together through two governors in Missouri.

More I-270 work is coming. IDOT's multiyear plan includes $115 million for an added lane from the canal to just east of St. Thomas Road, including a rebuilt Illinois 3 interchange. The states are coordinating to carry the third lane east toward Illinois 157. Expect orange barrels on our side of the river for a while yet.


What to watch

  • Next weekend: the westbound bridge opening, with lane shifts while traffic moves over.
  • Thanksgiving week: the first holiday rush on the twin bridges, if the opening happens on schedule.
  • Spring and summer 2027: median, guardrail and painting work, then a third lane each way.
  • Beyond: the added lane and Illinois 3 interchange work east of the canal, and the third lane's extension toward Illinois 157.

Sources